Mobile Steam Injection Boiler Truck Factory Acceptance Test Checklist

Use this Mobile Steam Injection Boiler Truck FAT framework to verify workmanship, controls, protection functions, documentation and agreed performance before shipment.

Published 2026-08-13 · By Vance Petroleum

Start with the job decision

Mobile Steam Injection Boiler Truck projects succeed when the equipment scope is tied to a defined operating duty: delivering controlled high-pressure steam for thermal recovery and mobile oilfield heating duties. A useful project document separates normal duty, maximum credible duty, standby or transient conditions and the physical interfaces available at site. This keeps procurement language connected to field reality.

Record steam rate, injection pressure, target steam quality and water-treatment needs as ranges rather than isolated peak figures. The supplier can then explain how the once-through steam generator, high-pressure feed pump, combustion and fuel skid and steam-quality monitoring package work together across the intended envelope.

Agree the FAT plan before manufacturing is complete

The inspection and test plan should identify hold points, witness points, acceptance criteria, required instruments and records. A FAT is not simply a visual factory visit. It should verify that the manufactured package matches approved documents and that controls and protection functions behave as agreed.

Review itemWhat to confirmEvidence or input
once-through steam generatorModel, materials, assembly and accessibilityApproved data sheet and inspection record
high-pressure feed pumpRotation, alignment, leakage and functional responseTest procedure and measured results
combustion and fuel skidCapacity, cleanliness, connections and service accessDrawing review and functional check
steam-quality monitoring packageI/O, alarms, trips and event recordsCause-and-effect test sheet
Mobile Steam Injection Boiler Truck factory acceptance testing and inspection
Record actual results, instrument IDs, open items and responsible closure dates.

Functional tests should follow the operating sequence

Test permissives, startup logic, normal control, alarms, controlled shutdown and emergency shutdown in a sequence that operators can recognize. Simulate relevant low, high and signal-failure conditions. If full-load testing is not practical at the factory, document the limitation and define the site acceptance test that will close it.

Do not release shipment with undocumented gaps

Compile signed test sheets, material and calibration records, final drawings, manuals, spare-parts lists, packing lists and the punch list. Classify open items by whether they prevent shipment, prevent installation or may be closed during commissioning. Photographs help, but they do not replace signed acceptance records.

Keep a usable project record

Maintain one controlled file containing the approved duty sheet, supplier clarifications, drawings, component data, inspection records, test results, deviations, photographs and signed acceptance documents. Record document revisions and the person responsible for each open item. This prevents the operating team from receiving a package whose final configuration differs from the information used during procurement.

The handover set should also identify installed component models, consumables, calibration intervals, recommended spares, preservation requirements and supplier support contacts. Capture baseline operating readings when the unit is accepted. Those records give maintenance personnel a reference for condition changes and allow later modifications to be reviewed against the original design basis.

Before closing the project, confirm that operators can find the startup, normal-operation, controlled-shutdown and emergency procedures relevant to their unit. Training attendance alone is not sufficient; the responsible team should demonstrate the required checks and know which conditions require escalation rather than continued operation.

Codes, standards and project requirements

Confirm the final specification and acceptance plan against the owner’s project standards, local jurisdiction and ASME Boiler and Pressure Vessel Code resources. The applicable project documents govern whenever they are more specific.

Frequently asked questions

What should a Mobile Steam Injection Boiler Truck FAT verify?

Verify conformance to approved documents, workmanship, component identity, controls, alarms, trips, records and the agreed functional test scope.

Can site performance testing replace the FAT?

They serve different purposes. The FAT finds manufacturing and logic issues before shipment; the site test verifies the installed package and actual interfaces.

More mobile steam injection boiler truck guidance

Steam Injection Trucks: Defining and Measuring Steam Quality — Steam quality describes the vapor mass fraction of wet steam. Pressure and temperature readings alone may not establish that fraction.

Oilfield OTSG Trucks: Feedwater and Steam Mass Balance — A once-through steam generator should be evaluated using consistent feedwater, outlet-flow and steam-quality measurements.